CSTR Anaerobic Reaction Tanks
Project: CSTR Anaerobic Reaction project --COFCO Huangkou Biogas Station
Tank dimension: Φ16.04-16.8m ; Volume: 3500m³
Relevant Requirements:
1. The feeding time to the CSTR reactor is 24 hours, and the raw material is pig manure.
2. The feed volume into the CSTR reactor is 150 m³/d.
3. The pH entering the CSTR reactor must be strictly controlled between 6 and 9, the internal temperature must be maintained at 35 ± 3℃ (temperature variation must not exceed 3℃/h), and TAC ≥ 1500. Other substances toxic or harmful to the biodegradation reaction are prohibited from entering.
4. Raw Material Parameters:
| Raw Material Indicators | Influent Flow Rate | TS | VS/TS | VS Gas Production Rate | SS | Total Nitrogen | Ammonia Nitrogen |
| Parameter Values | 150 m³/d | Fecal Liquid 1-10% | 40-50% | CH4 Content ≥55% | 30000 | 4500 mg/L | 4000 mg/L |
5. Gas production ratio per cubic meter of raw water anaerobic digestion: 15%
6.Design gas production capacity of CSTR reactor: 800 m³/d, actual operating capacity: 1100 m³/d;